| SITE MAP | CONTACT US | LOCATIONS | HOME |
Links

 
      

We provide here for your amusement some risk analysis problems to try.

If some of the techniques appear unfamiliar, you will find all the information you might need in ModelAssist. Have fun!

top


Insurance claim problem

Your company insures recreational light aircraft. Over the last 10 years there have been an average of 17 crashes per year. Legislation this year has increased your exposure: a crash will now cost you Lognorm(50,22) thousand pounds. You have not been able to increase your premiums though, and have the same revenue as last year of 1.09 million pounds.

Assuming the same level of exposure for next year, what is the probability that you will make a loss next year?

top


Portfolio of risk

You are faced with a number of risks (A to F) that may impact on your project. The size of impact is uncertain and specified by minimum, most likely and maximum values. The probability of each risk occurring is estimated below: some probabilities are conditional on whether other risks have occurred.

Determine the distribution of costs you might occur from these risks.

What is the probability that none of the risk events will occur?

Risk labels

Min cost

Most likely cost

Max cost

Probability that risk event
will occur

A

4

5

8

35%

B

2.4

3

4.8

40%

C

1.6

2

3.2

40%

D

2.4

3

4.8

7% if risk B doesn't occur,
70% otherwise

E

6.4

8

12.8

20% if risk A doesn't occur,
40% otherwise

F

4

5

62

20% if risks A and C don't occur,
40% otherwise

top


Bidding to construct a line of electricity pylons

Your company has been invited to bid for a project to design and construct a line of 16 electricity pylons. Estimates are based on PERT distributions (using absolute minimum, most likely and absolute maximum) unless indicated.

Design

The design work could be done in-house. However, if you are awarded an upcoming contract in France that your company has bid for, you will not have the resources to design this job and will have to sub-contract out. There is some disagreement about the probability of getting the French job, so it is also represented by a probability distribution.

Your designers estimate the following:

 

Minimum

Most Likely

Maximum

In-house design cost:

Ј150 000

Ј165 000

Ј190 000

Sub-contracted costs:

Ј180 000

Ј200 000

Ј235 000

Probability of French job:

 

40%

 

Foundation construction

Your foundation engineers estimate the following:

 

Minimum

Most Likely

Maximum

Material costs/pylon:

Ј6 200

Ј7 000

Ј7 900

Man hours/pylon:

Normal(600,80) dependent on
individual ground conditions at pylon sites

Cost/man hour:

 

Ј7.50

 

Total plant cost:

Ј250 000 

Ј300 000

  Ј380 000

Pylon construction

Your steel work engineers estimate the following:

 

Minimum

Most Likely

Maximum

Steel cost/pylon at construction time:

Ј52 000

Ј54 000

Ј58 500

Man hours/pylon (dependent on final pylon design):

200

240

270

Cost/man hour:

 

Ј13.00

 

Time constraints

The project's components are estimated to take the following time (weeks):

 

Minimum

Most Likely

Maximum

Design:

10

12

15

Foundations:

14

16

21

Time from foundation completion to last pylon completed:

4

4.5

5.5

The bid document has a clause specifying a 35 week completion time with a penalty of Ј25,000 per week or part thereof for overrunning.

  1. Produce distributions of the total project cost and duration.
  2. Use a scatter plot to illustrate the relationship between the project's cost and duration. Try plotting iterations above and below 35 weeks separately on the same graph and fit regression lines through the two data sets.
  3. Determine a suitable bid price you would be happy to offer.
  4. Which uncertain variable within the model is most influencing the maximum tail of the cost distribution?
  5. Rerun the model, but make the design time and cost 90% correlated and the time to do the foundations 80% correlated with the associated plant cost and 90% correlated with the total foundation man hours. What is the effect of including these correlations?

top


Women in a group

20 people have randomly been selected off the streets of a city. They write down whether they are male or female on a piece of paper and put them in a hat. You pick out 10 pieces of paper and read them. 6 are female. Estimate how many females are there in total in the whole group? (Hint: The problem is one of uncertainty, and lends itself well to Bayesian analysis.)

top


Sum of two equal independent uniform distributions

What is the shape of the distribution of the sum of two independent, equal Uniform distributions?

Too easy to give a model answer to, but could you work it out mathematically? What would the answer be if the two Uniform distributions had different ranges?

top


Estimating the size of an outbreak

100 people were exposed to some bacteria (eating food at a fair perhaps). The food was subsequently found to be contaminated and 10. They were all tested for the presence of infection by the bacteria.

Unfortunately, the testing method is not perfect. The test has a sensitivity of 0.65 (Sensitivity is the probability of testing positive given the patient is infected). The test has a specificity of 0.85 (Specificity is the probability of testing negative given the patient is not infected). 6 of the 10 people traced tested positive.

Estimate how many of the 100 people exposed are actually infected.

top


Meeting under the clock

Two people agree to arrive at the town clock sometime tomorrow at some time between 1p.m. and 2p.m., and remain for 20 minutes. What is the probability that they will be there at the same moment? (Assume that there is equal probability that they will arrive at any particular time).

top


Drinking from a bottle

There are 20 virus particles in a bottle of water. The water is poured into glasses in equal amounts and one person drinks each glass of water. A single particle has a 30% probability of infecting a person. How many people would be infected if a) there were 5 glasses, b) there were 10 glasses?

top

      
 
Legal Notice | Return/Refund policy | Privacy statement | Delivery terms
©Copyright 1997-2008 Vose Consulting. All Rights Reserved.